previous month  SEPTEMBER 2010  next month
S M T W T F S
   1234
5
678
9
1011
12
131415161718
19
202122232425
26
2728
29
30  
     
Upcoming Events
Thursday, September 9
  • Administrative Council Meeting
    7:30 PM to 9:30 PM
Sunday, September 12
  • Worship 9 a.m.
Sunday, September 19
  • Worship 9 a.m.
Bible Search
NOTE: Put quotations around your keyword search to find your exact phrase together.
 ex. love, "Jesus wept", sin
 
 ex. 2 Timothy 3:16
 
provided by biblegateway.com
New Church Building Timeline

Timeline of the Grey Eagle UMC New Building Project

Week of August 12, 2007

  • The building site was prepped for excavation by Art Johnson of Art Johnson Construction, and Duane Becker of Update Lumber and Supply of Grey Eagle. 
  • A sign proclaiming the future site of the Grey Eagle United Methodist Church was erected on the building site. 

Week of August 19, 2007

  • Excavation of the church site began.  Twardowski Excavation of Long Prairie prepared the land for laying the foundation. 
  • The cement block foundation was laid by Beuning  Masonry of Sauk Centre. 

Week of August 26, 2007

  • The groundbreaking ceremony was held on Sunday afternoon of Aug. 26. An antique one-bottom plow powered by members of the congregation was used to symbolically turn over the soil in what was a corn field just days earlier.  The use of the plow symbolized the agricultural heritage of the church and the importance of the congregation pulling together. 
  • A well was drilled by Atkinson Well and Pump of Freeport.  A strong flow of water was found at 52 feet. 
  • Backfill of the foundation and preparation for the septic system was completed by Twardowski Excavation. 

Week of September 2, 2007

  • Bitz Plumbing and Heating of Grey Eagle, installed the plumbing that runs under the floor.
  • Grey Eagle Electric installed the conduits and electric in-floor heat cables that run under the floor. 

Week of September 9, 2007

  • The cement floor was poured.
  • The framing walls were built by Art Johnson Construction. 
  • Sheeting went on over the framed walls.
  • Interior walls were constructed.

Week of September 16, 2007

  • Rafters were set in place.
  • Additonal interior walls were built.
  • Three people injured as 30 rafters fell into the interior of the building as a result of a wind gust. 

Week of September 23

  • The fallen rafters were removed and discarded.  The injured workers were healing well and the insurance adjuster came to complete the paperwork for an insurance claim. 
  • Interior walls and the platform at the front of the sanctuary were built. 
  • A very successful hog roast fundraiser was held at the Lake Country Storage building next to the church building site on Sat. Sept. 29.

Week of October 1

  • New rafters arrived and were installed on Wednesday.
  • Plywood sheeting was put on the roof to give it stability. 

Week of October 7

  • Steel roofing was completed on the north side of the building and partially on the south side.
  • Part of the main door canopy was built but dependent upon the shipment of a steel beam. 

Week of October 14

  • Most work on the building was halted due to rain that fell every day. 

Week of October 18

  • Windows and doors have been installed. 
  • The cement board siding is beginning to be installed. 

Week of October 25

  • Carpenters completed the steel roof. 
  • Plumbers installed plumbing lines for the restrooms and the kitchen.
  • Electricians installed electrical outlets and light fixtures.
  • Excavation around the parking area was completed. 
  • The installation of the sewer system was completed. 
  • A kitchen committee shopped for sizes and types of kitchen appliances. 

Week of November 4

  • Cement sidewalks and drivethrough area were poured. 
  • Electrical and plumbing work continued on the interior.

Week of November 11

  • Electrical and plumbing work continued on the interior. 

Week of November 18

  • More siding was installed on the ends of the building.
  • Stonemason, Tom Welck, began work on the stone facade.

Week of November 25

  • The interior walls of the church were insulated. 
  • More plumbing, heating and eletrical work was completed
  • Final specifications for the sound system were identified.

Week of December 2

  • The sheetrock was hung in the west end of the building: classrooms, kitchen, restrooms and fellowship hall.
  • The ceiling was insulated. 
  • Electrical and ductwork was done throughout the building. 
  • Framing of the front of the sanctuary was completed. 

Week of December 9

  •  The sheetrock was hung in the sanctuary. 
  • The pine ceiling was installed in the sanctuary.
  • Wiring for the sound system was completed.
  • Seam taping was begun in the fellowship hall, classrooms and kitchen areas. 
  • The in-floor electric heat was turned on in the west side of the building. 

Week of December 16

  • Work on finishing the sheetrock wall continued.
  • Work on the brickwork continued on the exterior. 
  • The kitchen and restrooms were measured for cabinetry.

Week of December 23

  • Paint colors were chosen for the interior wall.
  • Work continued on finishing the sheetrock walls.
  • Cabinetry was under construction. 

Week of December 30

  • More ductwork was completed in the ceilings.
  • Finishing work continued on sheetrock walls. 
  • The front doors were installed.

Week of January 6, 2008

  • Painting of the walls was underway.
  • Heating/cooling ductwork was completed. 
  • Sheetrock finishing continued. 

Week of January 13

  • Painting continued.
  • Two windows that will house stained glass were installed.  One is over the chancel area and the other is on the front of the canopy. 
  • More of the exterior siding was installed. 
  • Gridwork for holding the ceiling tile in the west end of the building was installed. 
  • More lighting was installed. 

Week of January 20

  • Painting and staining continued.
  • Kitchen cabinetry and interior doors were installed.
  • Ceiling tile was installed.
  • Vinyl floor covering was installed in the west end of the building--fellowship hall, kitchen and restrooms.

Week of January 27

  • Kitchen appliances were installed.
  • Plumbing fixtures were installed.
  • Entry doors and folding door was instralled. 

Week of February 3

  • Entry area ceramic tile was installed.
  • Restroom stall dividers were installed. 
  • A Venitcian finish on the curved walls of the sanctuary was begun.
  • The overhead door for the kitchen serving area was instralled.

Week of February 10

  • Painting, staining and varnished was completed.
  • Sanctuary entrance door was installed.
  • The water pump and pressure tank were installed. 
  • A crew of 12 people cleaned the church on Sat. a.m.
  • People gathered to write prayers and other messages on the sanctuary floor.

Week of February 17

  • The carpet was installed in the sanctuary, conference room and Sunday school room.

Week of February 24

  • The ceramic tile was laid in the entry.
  • The vinyl tile received the finish coat in the fellowship hall, kitchen and restrooms.

Week of March 2

  • Moving week.  A large crew of volunteers moved the furniture, supplies, and kitchen ware from the old church to the new. 
  • Crews of voluteers organized the kitchen, fellowship hall, conference room, Sunday school room and installed the sanctuary furniture.
  • The sound system was completed with the capacity to have sound in all rooms including an outside speaker under the canopy.
  • The sound system includes special devices for the hearing impaired. 
  • Crews of people cleaned all of the furniture. 
  • Crew of workers washed windows and organized the church for the first service. 

Week of March 9

  • The first service in the new building was March 9, 2008.
  • The final finish was applied to the Venitian finished walls of the chancel area.

Week of March 16

  • The first fellowship hall service was held March 20, an Agape Supper.
  • A service of Tennebrae was held on Good Friday evening.
  • Tom Welck continued to work on the stone facade on the exterior. 
  • The final coats of varnish were applied to some window casings.

Week of March 23

  • The first Easter Sunday breakfast was served in the fellowship hall.
  • The first Easter worship service was held.

 Week of March 30

  • Siding was installed on the front of the canopy.
  • The stone facade is completed around the entry door. 

Week of May 26

  • Tom Welck, stonemason, finished the stone work on the church.
  • Work on landscaping began and lawn seeding was completed.

WeeK of July 13

  • More trees and shrubs were added the the landscape.  The garden outside the south windows was completed. 

Week of July 20

  • John Roe, Rod Thompson, Karina Roe and Loren Roe completed the installation of an irrigation system to water the lawn, trees and shurbs throughout the church property.

 

comment posted by Lary Heida on 12-11-2007
Nice design. There is more space than I thought would be possible for the amount of money spent. Great job everyone!
Post a Comment
Your Name
Comment
Validation
Please duplicate the letters and/or numbers you see below to verify that you are a valid user of this form.
These are the letters you will duplicate in the box below.
Contents © 2010 Grey Eagle United Methodist Church | Site Provided by mychurchwebsite.net | Privacy Policy